Takt Time and Load Leveling

Lean Six Sigma, a methodology aimed at improving efficiency and eliminating waste, integrates Lean's focus on streamlining operations with Six Sigma's emphasis on quality and precision. Within this framework, "Lean Controls" play a crucial role in sustaining the improvements achieved through initial Lean Six Sigma projects. Specifically, within the realm of process management, two key concepts—Takt Time and Load Leveling—stand out as fundamental to implementing effective Lean controls.

Takt Time: Synchronizing Production with Demand

Takt Time is derived from the German word "Taktzeit," meaning "cycle time," and is a concept that aligns production rates with customer demand. It represents the maximum time allowed to produce a product in order to meet customer demand. Takt Time is calculated by dividing the available production time by the rate of customer demand.

The formula is as follows:



For instance, if a factory operates for 480 minutes a day and the customer demand is 240 units per day, the Takt Time would be 2 minutes per unit. This means every 2 minutes, a product should be completed to meet daily customer demand precisely.


The beauty of Takt Time lies in its simplicity and focus. By establishing a rhythm for production, it ensures that operations are neither overproducing nor underproducing relative to demand. This synchronization minimizes waste and ensures a steady flow of products, aligning production closely with actual customer needs.


Load Leveling: Smoothing the Production Process

Load Leveling, or "Heijunka," is a technique used to reduce fluctuations in a production process. It involves distributing production volume and variety evenly over time, thereby stabilizing the production system and supply chain. Load Leveling is crucial for absorbing the variability in customer demand and production capacity, making it easier to implement Takt Time effectively.

Implementing Load Leveling often involves the use of Heijunka boxes, which visually schedule production in a way that evens out the production of different product types over a certain period. This helps in managing resources more efficiently, reducing lead times, and increasing flexibility in responding to changes in demand.


Integration of Takt Time and Load Leveling in Lean Control

The integration of Takt Time and Load Leveling in process management underpins the Lean philosophy of continuous flow and just-in-time (JIT) production. By defining the pace of work (Takt Time) and smoothing out the allocation of work (Load Leveling), businesses can achieve a more balanced and responsive production system.

  • Enhanced Efficiency: Aligning production closely with demand through Takt Time while smoothing out the production process with Load Leveling leads to significant reductions in waste and idle time.

  • Improved Responsiveness: These concepts make it easier for businesses to respond to fluctuations in customer demand without the need for large inventories.

  • Greater Stability: Load Leveling reduces the pressure on workers and machinery, leading to a more stable and predictable production environment.


In conclusion, Takt Time and Load Leveling are instrumental in establishing Lean Controls within process management. They represent more than just tools; they embody a philosophy of operational excellence that prioritizes customer needs, waste reduction, and process stability. By embracing these principles, organizations can achieve not just temporary gains but long-lasting improvements in their operational performance.


Exercise 1: Furniture Factory Paint Process


Scenario: A furniture factory operates an 8-hour day, equating to 480 minutes of production time. To meet customer demand, 160 pieces of furniture need to be painted each day.


Objective: Calculate the Takt Time for the painting process to ensure the factory meets daily customer demand without creating a backlog.


Solution:

  1. Available Production Time: 480 minutes

  2. Customer Demand: 160 units/day

  3. Takt Time Calculation: Takt Time = Available Production Time / Customer Demand

Result: The Takt Time for the painting process is 3 minutes per unit. This means to meet customer demand, each piece of furniture should be painted within 3 minutes.

Exercise 2: Satellite Manufacturer


Scenario: A satellite manufacturer receives orders for 26 satellites per year. The company operates 260 working days per year.


Objective: Determine the Takt Time to understand the production pace needed to fulfill annual orders.


Solution:

  1. Available Production Time: 260 days/year (Assuming one shift per day and simplifying to 1 unit of work time per day for ease of calculation)

  2. Customer Demand: 26 units/year

  3. Takt Time Calculation: Takt Time = Available Production Time / Customer Demand

Result: The Takt Time is 10 days per satellite. This means the manufacturer needs to complete a satellite every 10 days to meet the annual demand of 26 satellites.

Video



Curent Location

/412

Article

Rank:

Takt Time and Load Leveling

379

Section:

LSS_BoK_5.1 - Lean Controls

C) Lean Control in Process Management

Sub Section:

Previous article:

Next article:

bottom of page